11h00 Welcome (lead partner)
11h10 WP1 –Exchange of experience activities (Lead Partner)
• Joint Report – State of Play (TC coordinator)
• COVID19 impact on the project activities:
o Project calendar (review and modification)
o Local Stakeholders Group meetings – State of play (all partners)
o Annual internal workshops – State of play (all partners)
o Other impacts (all partners)
12h00 WP 2 –Communication activities (Communication Manager)
• Summary of the communication activities developed since the last Steering Committee meeting
• Digital tools manual – State of play
• Project website – Access and usage statistics.
• Project social networks – State of play
12h30 WP3 –Management and coordination activities (Lead Partner)
• First execution report – state of play
• Second execution report – main recommendations
• Project technical and financial execution level (all partners).
13h00 End of the meeting