Increasing the energy efficiency within the High School with Sports Program, in the built developed surface of 4,488.40 sqm
1. Increasing the energy efficiency within the High School with Sports Program, in the built developed surface of 4,488.40 sqm - through thermal rehabilitation works of the anevelopa elements, the heating system and hot water consumption, works aimed at installing alternative systems for the production of electricity and thermal energy for own consumption, rehabilitation works of the lighting installation of the lighting system in the building and related measures - repair of the construction elements of the facade, construction of the roof type roof, including repair of the rainwater collection and evacuation system at the level of the frame type roof, the dismantling of the installations and equipment apparently mounted on the facades of the building, as well as their installation / reassembly after the intervention works, the restoration of the interior finishes in the intervention areas, the repair of the protective sidewalks and the creation of facilities / adaptation of infrastructure for people with disabilities, for a period of 24 months.
2. Decreasing the level of greenhouse gases from 214.50 to 92.82 tons of CO2 and primary energy consumption from 1,290,712.36 to 640,498.89 KWh / year, at the end of the project implementation, at the level of the High School with Sports Program.
3. Achieving a minimum level of at least 23.53% of the total primary energy consumption achieved from renewable energy sources, at the end of the project, at the level of the High School

Resources needed

The total value of the project 6.400.732,78 lei lei

Evidence of success

Increased energy efficiency in the building of the High School with Sports Program located on a built-up area of 4498.40 sqm.
The level of greenhouse gases decreased from 214.50 to 92.82 tons of CO2 and low primary energy consumption from 1 290 712.36 to 640 498.89 KWh / year, at the level of the High School building with Sports Program.
Minimum level of at least 23.53% of the total primary energy consumption achieved from renewable energy sources reached

Potential for learning or transfer

The GP can be replied in the first place by Alba Iulia Municipality on other public buildings and in the second place by other local authorities in order to reduce local emissions of CO2.
Project
Main institution
Alba Iulia Municipality
Location
Centru, Romania (România)
Start Date
January 2018
End Date
September 2020

Contact

Please login to contact the author.